Hello,
I am struggling to create a filter required by my owner between updates- below are the requirements:
"Activities within 14 calendar days of the critical path that were planned to occur during the updated period, but which did not occur or occurred later than the scheduled late start or late finish date, shall be identified and accompanied with an explanation for those delays."