Hi All,
Please can any one help me out on this issue; I have just built a new plan and fixed all links (Relationships) with the lags. Then I scheduled the plan and the contract start date changed to the scheduled date, which then changes the whole dates of activity on the programme. Please what do I need to do to keep the dates that has been given to me to use as the start date on the programme. (P6)
Many thanks.
Chuck.