Hi Guys,
i have a problem with s-curve of my project regarding actual and budgeted cost curve.datadate is may 10,2014 i did not understand why budgeted and actual cost's curve are not same curve before datadate.i entered budgeted and actual cost manual.i can send xer file.sorry for my english.i hope i could tell my problem.