I am trying to show my baseline bars and it seems they are pulling from the BL Project Finish dates which are not correct and do not match the BL Project Early Finish Dates
1. How can I correct this so my BL Project Finish dates match the BL Project Early Finish dates(which are correct)?
2. is there a setting to have the bars reference the BL Project early finish dates and not the useless Project Finish Dates.
If by global change can you please post the setup as I can not seem to create the proper global change to make it work.
Thanks
Mark