I need help, Im using P6 ver 8.2. Ive read some of the forums regarding using the calendar, its advantages and disadvatanges on this problem.
Heres the situation, Project operation was suspended for 60 days due to a Tower Crane Collapse.
Questions:
1. Whats the best way to present it to the client besides using the Calendar and marking those dates NON-WORK, Bar-necking and using a Curtain.
2. How to create an new activity to present the "TOWER CRANE COLLAPSE" as an activity, splitting those IN-PROGRESS/ON-GOING activities then reconnecting them once the project resumes. Is this the best way to present it?
Thanks guys!
engr RAUL UMALI
Planning Supervisor
Makati Development Corporation
Philippines