hi people,
I am new in planning, and It would be highly appreciated to answer my BASIC questions :)
- Have an activity which actually takes 12 hours but in 2 weeks, how I can plan it? already in my schedule, it started on 17th Feb and will finish 28th Feb., which is 80 hours for duration that is not correct, what is planning solution for this?
- the resource who is working on above job, is working on other four tasks as well. During in 2 weeks he is working 12 hours to finish mentioned job and other 4 tasks which not finish in 2 weeks. how I can show his work hours in my plan?
- Last question: why finding is not working most of the time? To search an activity ID I use find but doesn’t work! I Mean I can find manually but in finding window it says no result!
Thanks in advance guys!
Nikan.