Hi,
I have received a project schedule, it seems to have a baseline, but when I go to the Manage baselines, there is no baseline related to this schedule.
I tried creating a copy of the current project as the baseline (which would then be the only actual baseline related to this schedule), but what happens is it is either creating a copy of this imposed baseline as the baseline again... or it is simply not able to overwrite this imposed baseline which isn't actually set in the baseline management window.
I have been working with Primavera since 2005, P5 and I have not yet experienced this kind of issue.
The BL1 will not update or be overwritten and it does not exist in the Baseline management window so it acnnot even be deleted?
Any suggestions?