Can you please help me?
I have a Gantt chart with a Baseline and fully logic linked but as i record actual start and actual finish along with overall percentage complete the periods change, as they should. however i need to record progress not just against the view or table that im in, I need to record progress against the baseline.
The problem i am having is that, i set up a baseline so that i can monitor movement (slippage) on the programme against the intent, but as everything is link if i run a report against progress, the report would show that i'm not in delay even if it is late against the baseline.
what do i need to do, so i can run a report against a baseline?
Sorry if this sounds a bit gobbly, but i find it hard to explain....