HI all,
I have a large programme for direct lay cable installation and have now been asked to create a ducted version. I'm not seeing any big differences between the two.
I would imagine you can lay all the ducting during excavation and backfill the trenchs and then pull the cable once all the ducting is in? Cant really see any other schedule alterations that would be required?
Feel like I'm missing a few tricks here so any advice very welcome.
Cheers
Adam