Long time P3 user, was occassional now heavy P6 user. 3 things driving me crazy:
1). when I switch projects I always get the same default layout no what how I had left it, same with the filter. I want it to look like the last time I was in that file. It seems like it depends on what I was doing last in general. My layout section is a mess because I have so many, they need to add an organizational aid.
2). Also, if I open a file, then I open another file...how can I switch back and forth
3). When I try to assign a baseline to my current project it will not pull the exising choices up, to I have to also open the file I want to make a baseline?
John R