Hi Everyone,
This is my first post as I am a new entrant to planning. I am currently trying to estimate the productivity rates for ductwork and under in the M&E section, ducting is 1.2 to 1.5 sqm/day/man.
I am confused with the use of square meter. So ductwork of 800x600mm for a run of 10 meters would take, Ductwork Square meterage [(0.8+0.6)*2]*10=28, then 28/1.2= 24 days for single person crew??
Some of team member go by measuring volume; which is correct?
Also, there is a pump , one active on standby, each pair for a wet riser and the other for sprinkler. We have no idea but we put 15 days for installation? Am I close?
Thanks in advance!