· Updated engineering and procurement activities within our master schedule.
· Tracked field progress in order to update construction activities in our master schedule
· Monitored weekly and monthly deliverables from our contractor
· Made commentary on contractor’s schedule submittals to make sure our scheduling standards were being met/upheld
· Went over the 2week look aheads with our contractor to avoid negative float (falling behind)… when it did occur we planned on how to make up for lost time
· Created Manpower Forecasting reports from the contractor’s schedule