Dear Schedulers,
For some reason after importing my schedule in another computer with P6, my budgeted labor units slightly changes (from 805,700 manhours to 789,500); all user settings seem to be identical in both machines. Please help, I gotta get my baseline schedule approved shortly.
Thanks, Sean