I am trying to do a manual resource leveling and I would like to be able to focus on one wbs element at a time - unit. Is there a way to set up the profile so that it filters on wbs? I only want to see the resources for a specific unit not the entire project. It either cannot be done or I am missing something simple. Any thoughts appreciated. I am using P6 8.3. Thanks.