I have this problem at work: I have my time schedule which is updated up to data date, now a new area is going to be added to project scope which the engineering and construction activities have been started 2 months before. now thay ask me to prepare a time schedule for this new work and incorporate it to my plan. please guide me in this regard how can I attach this new schedule to the project schedule(considering that some activitie in both are done or progressed) next how shoud I incorporate this change to the baseline?