I wonder if anyone has experienced the same problem that we are getting here and that is that some of our ACTUAL Finish dates are disappearing from our schedule. During our progress updating period we check the box and input the date that an activity actually finishes on; however when we come to the next updating period we discover that some of these dates have disappeared, although the % complete stays at 100%. Has anyone come across this and do they have any idea why this is happening.