I cannot figure out how to showing Actual Work/%Complete without it afffecting Planned Start & Planned Finish. I know I can show a Baseline. But I want to be working "in-project" on the schedule and the %Complete is controlling Planned Finish dates, as shown on the bar even though they remain as desired in the Columns Grid. I have tried driving the bars with Current Bar, Planned Bar, etc. and cannot get the two dis-entangled.