Hi,
I have an activity that is showing as critical with zero float (total float and free float) that shouldn't be .... all of it's sucessors have at least 1 day float on them, it has no constraints, the planned start and finish, remaining early start and finish and remaining late start and finish all match the 'main' start and finish.
I've checked what is defined as being critical is anything with less than '0h' float - I don't think this should make a difference to this problem anyway as it's the number of days float on the activity that i believe to be wrong ... Any ideas as to why it would be showing zero float rather than one day?
Many Thanks,
Abbie