Dear All P6 Experts,
I have my current schedule and I already assigned Basline to it. I try to export my current schedule as XER file and send it by e-mail but the person who import it to his computer he can't see my assigned baseline? Is there method I can send them in correct way at the same time in one XER file?
Thank you all,