Hi,
A friend of mine working with a consultant, has a claim from the contractor. The client on the submission of the design drawings recommended a change within the 28 days of the submission. The contractor resubmitted the design and after a long period of arguments from both the sides the employer approved the original design submitted by the contractor.
Now the contractor claimed an EOT of 69 days when my friend inserted the delay in critical path that has a constraint the approved baseline, it showed the same but when he removed the constrained the delay was just 30 days.
Now, my question is can the consultant remove the constraint to analyze/ determine the delay?
CHEERS