hi to all experts,
I am working with a recovery schedule. Which has been progressed upto 23.50%. Now scope of my contract has been changed.before total project value was 50 millions.now after lots of change order it is 70 millions.& invoice already claimed upto 50% my question is should i load total revised cost i.e. 70 million on my schedule or should i load cost based on remaining work. any promptly reply will be highly appreciated. thanx in advance......