Guys,
I have my cost loaded schedule prepared in P3. I have made adjustments in cost using the global change then imported the p3 schedule in P6. After the successfull importing to P6, I noticed that the cost remains the same as if I have not made adjustment thru global change in P3. Also, the budgeted quantities have been changed.
please help me in this issue.
thanks,