Hi All,
I was importing programme from MS project to P6.It's quite difficult to assign a baseline on the progress programme,because everymonth there will be new activities added to MS project.So when import this to P6 and assigning the baseline to this takes a lot of time.
Is there a quick way to fix this.
Comments and help appreciated from everybody.
Thanks,
Rinet