Hi to All,
I am trying to do on P6 (V7) what I used to do when I was working on P3 a several years ago.
I used to generate my S-Curves on Excel from P3 by computing a Tabular Report displayed the following way :
Time | Early start | Late Start | Early Finish | Late Finish |
Month 1 | Budgeted Units | Budgeted Units | Budgeted Units | Budgeted Units |
Month 2 | Budgeted Units | Budgeted Units | Budgeted Units | Budgeted Units |
It was extremely useful and very easy to generate Early & Late Curves as well as forecast curves.
What I see today from P6, is only a way to export to Excel, the distribution budgeted units on a singular date but not Early and Late dates
How can I do that ?
Thanks very much in advance Planning Community
NB