I was wondering whether I can put in actual in Resource Assignments tab on the left, and i don't want it to split evenly.
For example
Monday 7 Hours
Tuesday 10 hours
Wednesday 3 Hours
The actual units in the table just grey out not allowing me to key in anything...:( please help... is there another way of put in actual day to day figure??? please help...