Situation: 4 calendars - Office 5 8s, Field 6 10s, Construction 5 10s and Elapsed Time 24/7. How do I get PRA to properly import the durations developed in P6 8.2 by day? Finding it difficult to think in terms of hours for a 2-3 year project. Any thoughts appreciated. Thanks.