Dear Sir,
I am in a very tragic situation with the schedule tracking with regards to the remaining early start date. In my schedule the remaining start for certain activity shows equal to data date. But as per the pratical situation at site, the actvity will not be done on this date.
- Activity - footing concrete % complete (duration) is 88%, remaining start is 1st June 12 (datadate) and remaining duration is 2 days.
- Actually at site we need another 15 days to complete the activity, it should show an end date of 17th june,
- if I change the remaining duration, the % complete changes.
- Is there anyway I can keep the end date as 17th june without altering the % complete, please help.
Thnaks in advance
Sridevi