When I scheduled a project I found an activity with finish date jun15 and as of may 1st datadate it is showing -212 d varience in BL-finish , actual % complete of that activity is 95% why that activity showing -212days of delay..?My question is
any mistake in selecting VARIENCE BL-FINISH in delay analysis ...is it correct?
Regards
Sunil.