My activities have multiple assignments of the same resource. However when I export and then import the programme there is only one assignment of that resource.
E.g. an activity needs 8 installers, so I allocate "installer" 8 times.
When re-imported only 1 installer is there and the budgeted hours are one eigth what they should be?