hi ,
I am new in Primavera P6, I am facing problem in allocating overtime to an activity.
Suppose i have one activity which is of 5 days, and worker normal working is 8h/d , and one resource work on this activity whose rate is $100/h . So total cost of this resource is $4000/5day . If on 5 days this resource work for 2h overtime , total overtime working hour is 10h/5days. Rate for overtime working is $200/h . So total overtime cost is $2000/5days .So total cost for 5 days is 4000+2000=$6000/5days Now where to
1) Define overtime rate (i.e $200/h) in Primavera P6....?
2) How to see total $6000/5days in Primavera P6...?
Kindly guide inputs in primavera P6 regarding Overtime allocation.
Regards