Dear All valued members
Q. I have 14 small projects (similar in scope with small variation in details, scattered all over the country) which are planned in separate 14 programs but they came under one contract.
For EOT purposes I am supposed to show all projects in one master program (Master baseline and then there will be Impacted Master baseline) to depict the EOT entitlement. can anyone suggest how to do that in Primavera v3/3.1.??