guys, need some help here...
I have my resource/cost loaded schedule. Cost is assigned by providing it in the Budgeted Cost for each activities. However, when I'm viewing the resource usage spreadsheet on weekly timescale, the weekly cost for each actvities is calculated on monthly basis, which must be of course should be in weekly too. as i generate the cost tabulation/report it gives me the same loading as the resource usage spreadsheet which is wrong..I did change the Admin Preference Option so the interval to summarize & store resource spreadsheet will be on weekly basis but still i got the wrong one...i'm using p6.
hope someone could help and advise me how to fix this.
thank you,
ariel