I have a project with 19,000 activities. When I copy this Project from one EPS Node to another, only some of the activities & only some of the activity codes copy over. I have tried the regular copy & paste at the Project Level, I have Exported it & the Imported it back in, I have copied it at a WBS Level. None of these have worked. What am I doing wrong?