START Date:
September, 2009
END Date:
August, 2011 - Preparation of EPC and Construction Schedules (Total Direct Man-hours = 15.500.000)
- Preparation of Progress Measurement Systems and Integration with Other Departments
- Preparation of Project Controls Procedures
- Preparation of Payment Certificate (for Kashagan Tranche 3 Power Generation Plant EPC Contract)
- Personnel Time Recording Database Setup and Management
- Updating and Forecasting Works with consolidated EPC Schedules.
- Monitoring Variations over Scope of Work
- Preparation of Daily, Weekly and Monthly Reports
- Supporting Preparation of Budget