Hi, every body.
I'm encountering the follow problem:
after schedule the activities bars are splitted / divided.
I've used :
- Physycal % of calculation (insert the % value)
- I've used the setting an expexted date and not
- not any resouces are loaded
- all links are FS =0
- there are not constrain
Pleas, somene can tell me why this happen,
thanks
Pierfrancesco