Hi Everyone,
Gday.
Just a quick one. I got a Programme of the 12 months contract project. We're already completed the first quater and we have status several activities. I have not assign any baseline programme and we're just having BL and BL1 as "current project" as default however I wonder why the BL bar and Current bar are coming different.
I'd love to hear any ideas.
Cheers,