I have loaded my P6 schedule with 17 resources and I have entered "planned" units resource numbers for each resource/each activity.
When I pull up the resource graph, the planned units only show up in the first month (for example: 3 month activity with 96 hours... all 96 hours are in month one).
I know this is a setting somewhere. I've searched, but no luck.
Thanks! Bill