Dear Planners,
I have encountered a problem in filtering the Look Ahead schedules wherein some of the activities that is ongoing does not appear on the look ahead schedule. in principle this must be shown. Tried to look into the samples of the look ahead schedule in P6 but seems it is not working.
Any help please.
Thanks