Guys,
I have developed a schedule in P 6.0, with resource loading. Following is the problem I am facing when viewing the Resource Usage Profile. The calender for both activities and resource selected is common 7 x 24 hrs.
I have say a resource mason with Defaults Units / Time : 8/d
Max Units / Time: 200/d ( ie 200 / 8 = 50 nos for the project duration)
Have assigned this to an activity PCC from 01.06.11 to 26.06.11 (25 days duration)
Now I want to allocate 8 masons for 25 days so have entered in Remaining Units / time : 64/d ( 8 * 8 ie 8 masons * 8 hrs / day for the entire 25 day durations)
But when I view in the Resource Usage Profile, I am able to view mason being allocated to only at the start of the activity and not being spreading all along the 25 day durations.
Rohit