Hi,
I have developed a schedule that is resource loaded with cost entered for the standard rates per hour for the respective resource. It is baseline,tracked and updated to date. In the calculation tab along with the task information for EV calculation % Complete is selected.
Now when I view the EV and EV Cost and Schedule Indicators (table - more tables), the BCWS and BCWP are indicating a value of 0, so are the various fields like SV, SV%,SPI,CV,CV%,CPI are also resulting in the value of 0.
Any suggestions to rectify this problem.
Rohit