Dear Friends
I joined as a planner in a water pumping station project . My first task was to
revise the delayed base program with out changein the Project finish dates.
I changed some relations of the activities and I have completed that task.
Now my real problem starts here.I dont want to delete the completed activities.
The same actual dates I want to show as planned dates in my revised program.My intension is to show the planned bar and Acyual bar in same time.
Dear Experts please help me in this issue ...
Regards
Arun .V