I imported a programme from P3 t P6. In the P3 version of the programme, 1-day work occupied the whole 1 day, but in P6 it only occupied an 8-hour period. I changed the calendar to solve this. But one thing I cannot changed is the data date. It is located 08:00 of the start date instead of at the very beginning of the day. My duration is set in days, not hours. Can someone help me.