Dear All,
I have assigned man-hour resources to each of all the activities in my construction schedule, but before I did that, I copied an existing resource with a default unit per time = 1.25/day then I set it to 10/day and assigned to all the activities. Afterwards, I loaded with budgeted man-hours. When I cheked in the resource assignment, man-hours loaded to all the activities is the same, BUT the budgeted unit shown in the wbs level is 125% higher than the summation of all activities under this wbs and this is similar to the report when it is generated. Why is this happen? Please Help!
Regards,
Jash