Dear Friends,
I am working in a building constrcution project ( MEP Works ). main Contractor has revised the baseline program due to delay in strctural works. As a MEP contractor how we can analyse to identify what are the changes has been done to base line program.
What are the things to be checked in the new revised program???? . Could any one explain me step by step procedure for analysing the new targeet program.
Revised target program has been made in such a way that
1) 4 months delay in project completion
2) All the MEP detail activities are removed & only they have kept 3 activities ( MEP 1st fix,2nd fix,final fix) in each level
3) Duration slot for mep fixs in each leve remain unaltered
Cheers,
Saud