i have just moved from using p3 to p6v7, its pretty different and i'm really missing the way p3 would calculate in reports! anyway, thats irrelevant now and I need to report daily progress against my schedule, based on resources.
my schedule is set up so that the duration type is fixed unit per time and % complete type is physical. is this the best set-up for me to calculate actual resource usage? i am finding entering actual data quite time consuming at the end of every day as there are a lot of activities to update, but when i've tried using unit or duration % complete, the auto-calulations arent true to how the task is progressing.
Also, is there a report i can set up to let me know achieved man hours to date, and also during the last 24 hours?
thank you for your help!