Hi,
Actually I'm preparing draft schedule for Precommissioning & Commissioning schedule for LNG Terminal Project.
And I come out with these activities as follows:
Precommissioning:
1. Hydrotest of Pipelines
2. Leakage Test of Pipelines
3. Flushing & Cleaning of Pipelines
4. System dry-out
5. Inerting
6. Systematic Conformity Check of Equipment
7. Static, De-energized Test of Equipment
Commissioning:
1. Preliminary Check
2. Functional Check
3. Operational Test
4. Pre-Startup activities
May I ask some advise to those who had the same experience on the questions below:
Q1. Are the activities and sequence are correct?
Q2. Is there any missing activity?
Q2. Are these set of activities can be applied to both Utility System & Process System?
Thank you and Regards,
Angel