Hello Friends,
I am facing a problem while assigning a baseline.
I have a updated project schedule( in P6V7). Certain activities are completed, cetain in progress and others not started. Now I want to assign my current project as the baseline so that my baseline start and finish dates match my start and finish dates. But while going my the normal process of maintaining and assigning a baseline, The dates are not matching.
Please someone help me solve the issue.
Regards,
Sheju