We removed hundreds of links between activities in two different WBS's. Now we realize that wasn't the right move and need to re-link everything.
The first thought is to do it maually, which will take a while. However, before removing the links I had created a copy (XER) and a reflection of the project. Is there a way I can r bring the activities and all their links (internal and external) from either the XER copy or the reflection into the source/current project?
Thanks.