Dear Planners,
I need to create a staffing plan by discipline. The staffing plan needs to be based on heads (name+lastname), for instance:
(manhours)
Civil wk1 wk2 wk3
Eng.1 40 20 20
Tec 1 40 40 40
Tec 2 20 10 10
I have loaded my schedule with budgeted units per activity at the level of one resource, for instance civil (670 hrs).
Is there a way in P6 to convert my budgeted units per activity into people (by name) per discipline.
The staffing plan is normally done in Excel.
Due to my manhours (budget) are already in P6, I would like to have the same source of manhours.
Any planner in the world with the same thought ???
Cheers,