hello all
i need your help.
i need to give weight to each activity in the project.
for exmaple here are some activity's i'm dealing with:
1-purchase.=10%
2-Infrastructure installation=30%
3-instrument installation=40%
4-delivery=20%
for each activity i need to take the percent of the activity that finished and calculate a diffrent weight in percentages